New build in Spain: how your deposit is protected

If you pay a developer in Spain before the home is finished, the law makes the developer guarantee that money: from the moment it holds the building licence, every advance payment, taxes included, plus legal interest must be covered by a surety insurance (seguro de caución) or a joint bank guarantee (aval) issued to you individually, and the money must go into a special bank account. If building does not start or the home is not delivered on time and the developer does not refund you within 30 days of your formal demand, the insurer or the bank pays. After handover, defects are covered for 10 years, 3 years and 1 year, counted from the reception of the works.

  • Ley 38/1999 · DA 1.ª, Uno y Dos.1 h); art. 17.1 · (source data as of 2026-10-08)

    source: www.boe.es · act.php

What does the guarantee cover?

Every amount you hand over towards the price, the taxes on it included, plus the legal interest on money from the day of each payment. The guarantee is either a surety insurance policy (seguro de caución) with an insurer authorised in Spain or a joint guarantee (aval) issued by a bank.

It must exist from the moment the developer obtains the building licence. An insurance policy is individual: one per buyer, naming the home you are paying for. The developer pays the premium until the deed of sale, and the insurer cannot refuse you because the developer failed to pay it.

  • Ley 38/1999 · DA 1.ª, Uno.1 a), Uno.2, Dos.1 a), c) y e) · (source data as of 2026-10-08)

    source: www.boe.es · act.php

Where does your money go?

Into a special account at a bank, kept apart from all the developer's other funds, which the developer may use only for building the homes. The bank may open that account only after it has required the guarantee.

What must the contract say, and what do you receive when you sign?

A purchase contract with payments before completion must state:

  • that the developer will refund what you paid, taxes and legal interest included, if building does not start or finish on the agreed dates, or if the licencia de primera ocupación, the cédula de habitabilidad or an equivalent document is not obtained;
  • the name of the insurer or the bank that gives the guarantee;
  • the bank and the special account into which you pay.

When the contract is signed, the developer hands you the document of the guarantee made out to you and to the amounts you will advance. Advertising for homes sold before or during construction must name the guarantor and the bank of the special account.

What happens if the home is not delivered?

If building has not started or the home has not been handed over, you choose: end the contract and get back what you paid, taxes and legal interest included, or give the developer an extension, written into the contract with the new completion and delivery date.

You first demand the refund from the developer in a way that can be proved. If the developer does not pay within 30 days, you claim from the insurer, which must pay within 30 days of your claim; if the developer cannot be claimed from, you go to the insurer directly. If the guarantee is a bank guarantee (aval), after the same 30 days you claim from the bank that issued it — or directly, if the developer cannot be claimed from; the law sets the bank no deadline to pay, as it does the insurer.

A bank guarantee expires if 2 years pass after the developer's breach without you demanding the end of the contract and the refund.

  • Ley 38/1999 · DA 1.ª, Dos.1 h), Dos.2 b) y c) y Cuatro · (source data as of 2026-10-08)

    source: www.boe.es · act.php

When does the guarantee end?

When the competent authority issues the licencia de primera ocupación, the cédula de habitabilidad or an equivalent document allowing the home to be lived in, and the developer proves it has delivered the home to you — or that you refused to receive it.

Which of these documents applies and which office issues it depends on the region and the municipality; the law names all three.

What if the developer took money without a guarantee?

It is a consumer-protection infringement, and the fine can reach 25 % of the amounts whose refund had to be guaranteed.

Defects after handover: how long they are covered

The periods run from the reception of the works without reservations — the handover from the builder to the developer — and not from your deed. The developer answers to buyers jointly with everyone who took part in the construction.

Liability for material damage to the building
What How much Where to check
Structure: foundations, beams, slabs, load-bearing walls 10 years art. 17.1 a)
Habitability: building elements and installations 3 years art. 17.1 b)
Finishes, answered by the builder 1 year art. 17.1, párrafo segundo
Deadline to claim, from when the damage appears 2 years art. 18.1

Which insurance is mandatory?

For a building whose main use is housing, only the ten-year insurance against material damage to the structure, with an insured amount of at least 100 % of the final cost of the works.

The law also describes guarantees for habitability and for finishes and allows the Government to make them mandatory by royal decree; the consolidated text of the law mentions no such decree. A notary will not authorise, and the land registry will not record, the deed declaring the new building without proof that the guarantees are in place.

  • Ley 38/1999 · art. 19.1, 19.5 c), art. 20.1; DA 2.ª · (source data as of 2026-10-08)

    source: www.boe.es · act.php

What can you check before paying the developer?

What the law requires can be checked in documents:

  • the building licence has been granted;
  • the guarantee document is made out to you, names the home and covers the amounts with taxes;
  • the payments go only to the special account named in the contract;
  • the contract names the insurer or the bank that guarantees the advances.
  • Ley 38/1999 · DA 1.ª, Uno, Dos.1 a) y Tres · (source data as of 2026-10-08)

    source: www.boe.es · act.php

How does this compare with the other countries of the site?

The same questions, answered by each country's own law, side by side. Each figure and article comes from the country's own sources, with a link to them.

What to compare Portugal Spain Poland Belgium
Legal protection of deposits and advance payments no mandatory rule — only a claim against the seller for double the deposit; the law requires no guarantee, insurance or escrow account Código Civil (Decreto-Lei n.º 47344/66), art. 442.º n.º 2 · 2026-10-07 required by law Ley 38/1999, DA 1.ª, Uno.1 a) y b), Uno.2 · 2026-10-08 required by law Ustawa o ochronie praw nabywcy lokalu mieszkalnego lub domu jednorodzinnego, art. 6–8, art. 46–49 · 2026-10-09 required by law: a bond of 5 % of the building price lodged by an accredited contractor; otherwise a completion guarantee from a bank or insurer, or a guarantee of refund of the sums paid Arrêté royal du 21 octobre 1971, art. 3 et 4 (loi Breyne, art. 12) · 2026-10-09
Mandatory construction insurance no mandatory rule — the technical professionals carry third-party liability insurance, which is not insurance in the buyer's favour Decreto-Lei n.º 84/2021, arts. 22.º–25.º: responsabilidade do profissional, sem seguro · 2026-10-08 Lei n.º 31/2009, art. 24.º n.º 1 · 2026-10-08 required by law Ley 38/1999, art. 19.1 c); DA 2.ª, Uno · 2026-10-08 no mandatory rule — the buyer's money is protected by the escrow account and the DFG guarantee fund, not by insurance of the works Ustawa o ochronie praw nabywcy lokalu mieszkalnego lub domu jednorodzinnego, art. 6 ust. 1 · 2026-10-09 required by law Loi du 31 mai 2017 (assurance décennale), art. 5; art. 2; art. 21 · 2026-10-09
Defect liability period 10 years / 5 years Decreto-Lei n.º 84/2021, art. 23.º n.º 1 · 2026-10-08 10 years / 3 years / 1 year Ley 38/1999, art. 17.1 · 2026-10-08 5 years Kodeks cywilny, art. 568 § 1; ustawa o ochronie praw nabywcy, art. 41a · 2026-10-09 10 years for defects that threaten the building's stability or solidity — architect, contractor and seller Code civil (ancien), art. 1792 et 2270, art. 1792 et 2270 (loi Breyne, art. 6) · 2026-10-09
Late delivery: what the law provides general rules: double the deposit back or specific performance Código Civil (Decreto-Lei n.º 47344/66), arts. 442.º n.os 2 e 3, 808.º · 2026-10-07 rescission with refund and legal interest, or an extension Ley 38/1999, DA 1.ª, Cuatro · 2026-10-08 an extra 120 days deadline set by the buyer, then withdrawal without costs and a refund; the contractual penalty is kept Ustawa o ochronie praw nabywcy lokalu mieszkalnego lub domu jednorodzinnego, art. 43 ust. 1 pkt 6 i ust. 3; art. 44 · 2026-10-09 compensation fixed in the contract, at least a normal rent of the finished home Loi du 9 juillet 1971 (loi Breyne), art. 7, f · 2026-10-09
Staged payments to the developer no mandatory rule Código Civil (Decreto-Lei n.º 47344/66), art. 410.º: forma do contrato-promessa, sem regime de pagamentos · 2026-10-07 no mandatory rule Ley 38/1999, DA 1.ª, Uno.1 b): cuenta especial; calendario de pagos no regulado · 2026-10-08 payments into the escrow account after each completed stage; each stage between 10 % and 25 % of the cost (open account) Ustawa o ochronie praw nabywcy lokalu mieszkalnego lub domu jednorodzinnego, art. 8; art. 24 ust. 2 · 2026-10-09 a deposit of at most 5 % of the total price; at the notarial deed, the land and the works done; then instalments never above the works done Loi du 9 juillet 1971 (loi Breyne), art. 10 · 2026-10-09
  • Ley 38/1999 · DA 1.ª; art. 17.1; DA 2.ª · (source data as of 2026-10-08)

    source: www.boe.es · act.php

Which taxes does a new home carry?

On the developer's first sale of a new home, VAT is due at 10 % on the mainland and in the Balearic Islands, garage spaces and storerooms sold with it included. In the Canary Islands IGIC applies instead of VAT, and in Ceuta and Melilla IPSI. The taxes on the deed are set by each autonomous community and belong to the calculation of purchase costs.

  • Ley 37/1992 · arts. 3.Dos.1.º y 91.Uno.1.7.º · (source data as of 2026-10-08)

    source: www.boe.es · act.php

Buying property in Spain: taxes, notary, land registry and the cash you need · Non-resident tax in Spain after buying a property

What this page does not contain

Some answers depend on documents this page has not read:

  • the legal interest rate on money — it is set every year by the Spanish budget law;
  • which municipal document your region requires before you can move in, and how long it takes;
  • how banks lend for a home still under construction and when a developer's loan can be taken over;